19 Nov 2026
Century Lithium said the US Bureau of Land Management, in a letter dated 13 November, accepted all baseline studies for its Angel Island lithium project in Nevada and set an Environmental Impact Statement as the review level under federal environmental law. The federal permitting dashboard shows a target of 4 February 2028 for the Record of Decision. The project is designed for 5.5 Mt a year of mill feed and average output of 27,400 t a year of lithium carbonate.
Source (Century Lithium release): https://www.prnewswire.com/news-releases/century-lithium-receives-notice-of-completion-and-acceptance-of-baseline-studies-for-angel-island-lithium-project-nevada-usa-302944712.html
Coverage (Securities.io): https://www.securities.io/blm-sets-eis-review-for-century-lithiums-angel-island-project/