17 Nov 2026
Delta Lithium's scoping study for its Mt Ida project in Western Australia shows an NPV of A$748m, a 33% IRR, pre-production capital of A$483m and a 4.3-year payback over an 11-year life including construction. A 1 Mtpa whole-ore-flotation plant would make SC5.5 spodumene, lepidolite and tantalum concentrates, with about 73% overall lithium recovery and unit costs of US$756/t concentrate. The study has +/-40% accuracy and includes Inferred material. Mt Ida is fully permitted.
Source (Delta Lithium ASX release): https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-03162443-6A1355315
Summary by Lithium Market Intelligence. Not investment advice. See the original source for full details.