Standard Lithium targets SWA Project FID by Q1 2027

12 Nov 2026

Standard Lithium said it expects a final investment decision on its South West Arkansas Project by Q1 2027, followed promptly by construction, with project financing the key remaining workstream. Binding offtakes with LG Energy Solution and Trafigura now cover up to 20,000 tonnes per year of battery-quality lithium carbonate for 10 years, above the initial target of about 18,000 tonnes from 22,500 tonnes of nameplate capacity. Cash stood at US$118.1 million at 30 September, with no term or revolving debt.

Q3 2026 results release (SEC): https://www.sec.gov/Archives/edgar/data/1537137/000117184326007401/exh_991.htm

Summary by Lithium Market Intelligence. Not investment advice. See the original source for full details.